Meghalaya Has 17 Centrally Funded Projects Yet to Show Any Physical Progress: DoNER Report

Shillong, June 14, 2026: A latest monitoring report from the Ministry of Development of North Eastern Region (DoNER) has flagged implementation delays in Meghalaya, with 17 out of 81 ongoing centrally funded projects recording zero physical progress as of May 2026.

The findings underscore persistent challenges in translating sanctioned funds into on-ground development in the state, even as several other projects have reached advanced stages or completion.

Key Highlights from the DoNER Report

According to the May 2026 report:

  • 17 projects remain at 0% physical progress, described as “non-starters” despite being listed as active.
  • Breakdown by scheme:
  • 6 projects under North East Special Infrastructure Development Scheme (NESIDS-OTRI)
  • 2 road projects under NESIDS-Roads
  • 3 projects under Prime Minister’s Development Initiative for North East Region (PM-DevINE)
  • 6 projects under North Eastern Council (NEC) funding
  • On the positive side, 14 projects worth over ₹200 crore have achieved 100% physical completion.
  • Another 32 projects have crossed the 75% completion mark.

These stalled initiatives span critical sectors including infrastructure, water supply, education, sanitation, and livelihood programs, potentially affecting local communities across Meghalaya’s districts.

District and Scheme-Wise Overview

East Khasi Hills district continues to lead the Northeast with the highest number of ongoing DoNER-supported projects (around 44), reflecting its prominence in regional development investments. Meghalaya accounts for a notable share of the total projects monitored by DoNER across the eight North Eastern states.

Scheme-wise distribution in the state includes:

  • 41 projects under NEC
  • 27 under NESIDS-OTRI
  • 8 under PM-DevINE
  • 5 under NESIDS-Roads

Completed Projects and Achievements

Notable fully completed projects mentioned in the report include improvements in water supply schemes (such as Greater Sohra), school infrastructure upgrades, literacy programs, livelihood centres focused on water hyacinth crafts, and handloom production facilities. However, only a portion of these completed works have achieved full financial closure, indicating pending administrative formalities.

Challenges and the Way Forward

Common hurdles for North East projects — difficult terrain, land acquisition issues, fund release conditions, and capacity constraints at the implementation level — are often cited as reasons for delays. The report serves as an important checkpoint for both central and state agencies to identify bottlenecks and accelerate execution.

As Meghalaya pursues its long-term development vision, timely resolution of these stalled projects could deliver significant benefits in connectivity, basic services, and economic opportunities for residents. Stakeholders await coordinated action to ensure that development funds result in visible progress on the ground.